Millbrook Roundabout Reconstruction - Phase 3

Millbrook Rab Phase 1 End Scc News Original[1] 0

Phase 3 of the Millbrook Roundabout works commences on Monday 7th January and is set to last until Sunday 3rd March. Phase 3 includes the south east quarter of the roundabout and First Avenue southbound up to City Depot (see map below).

Phase 3 Third Avenue Access

There will be no access into or out of Third Avenue at the west end. Access to Third Avenue during this phase of work will only be possible via the east end at the junction with Regents Park Road or the slip road opposite Adams Morey. To maintain access to the trade park, the west end of Third Avenue will become two way for the duration of Phase 3 (weather permitting).

You can find out more by visiting Southampton City Council's website. Here you will also find videos demonstrating the diversion routes for each phase of the works, including the video for Phase 3. You can also follow @scchighways on Twitter for up-to-the-minute travel information or email roadworks@southampton.gov.uk for further information. For advice on how to travel with minimum fuss throughout the works, take a look at our top tips here.